Whether you’re constructing a new commercial building, renovating an office space, or planning a tenant improvement project, one question consistently arises early in the process: How long does it take to get a building permit?

The answer is nuanced and depends on several factors—including project type, jurisdiction, completeness of plans, and local agency workloads. In this comprehensive guide, we’ll break down the timelines, stages, and key factors that influence the building permit process so you can plan smarter and avoid costly delays.


What Is a Building Permit?

A building permit is an official approval issued by a local government authority that allows you to begin construction or renovation work on a property. Permits ensure that projects comply with local building codes, zoning laws, fire safety, energy efficiency standards, and public health regulations.

Projects typically requiring a building permit include:

  • New commercial or residential construction
  • Interior build-outs (restaurants, offices, retail)
  • Structural modifications
  • Electrical, plumbing, or mechanical work
  • Major renovations or additions

Why Building Permits Matter

Failing to secure a building permit can lead to serious consequences, including:

  • Stop-work orders
  • Fines and penalties
  • Legal liabilities
  • Issues with insurance or financing
  • Difficulty selling or leasing the property in the future

Beyond legal compliance, permits ensure that your project is safe and aligned with engineering and architectural best practices.


Typical Timeline: How Long Does It Take to Get a Building Permit?

The time it takes to get a building permit can range from 1 week to 6+ months, depending on the following variables:

🧱 Project Type and Complexity

  • Minor Interior Renovation: 1–3 weeks (if plans are straightforward and stamped by licensed professionals)
  • Change of Use / Occupancy: 4–8 weeks
  • Ground-Up Construction (Commercial): 3–6+ months (due to plan review, site inspections, environmental review, and utility coordination)

🏢 Jurisdiction and Location

Every city or county has its own building department. For example:

  • Houston, TX: Commercial projects can take 4–8 weeks for initial review.
  • Austin, TX: Timeline may extend due to strict zoning overlays and sustainability requirements.
  • Unincorporated Counties: May move faster, but lack digital submission systems.

📑 Completeness of Permit Submittal Package

Submitting complete, code-compliant documents from the start dramatically speeds up the process. A full package typically includes:

  • Architectural plans
  • Structural, mechanical, electrical, and plumbing (MEP) drawings
  • Site plan and zoning information
  • Energy compliance documents
  • Licensed professional stamps

👷 Agency Workload and Staffing

Permit delays are common during peak construction seasons or due to under-resourced departments. Staffing shortages, internal audits, or city-wide policy changes can impact timelines.

🔁 Plan Review Revisions and Resubmissions

If your application is incomplete or has code conflicts, the permit office will request revisions. Every resubmission can add 1–3 weeks to the process.

Tip: Work with experienced architects and permit expeditors to avoid unnecessary cycles.


The Building Permit Process: Step-by-Step Breakdown

Understanding each phase of the process will help you plan for approvals more effectively.

1. Pre-Design Due Diligence

Timeframe: 1–2 weeks

  • Zoning verification
  • Property setbacks, use allowances
  • Utility connections
  • Floodplain research

2. Permit Set Preparation

Timeframe: 2–6 weeks (depending on project size)

  • Architectural, structural, and MEP plans prepared and sealed
  • Energy calculations completed
  • Coordination with engineers, consultants

3. Permit Application Submittal

Timeframe: Same day to 1 week

  • Application submitted via city portal or in-person
  • Fees paid upfront

4. Initial Plan Review by City Officials

Timeframe: 2–8+ weeks

  • Zoning, structural, fire safety, energy, and health departments review plans
  • Comments issued for revisions (if needed)

5. Revisions & Resubmittal (If Applicable)

Timeframe: 1–3 weeks per round

  • Applicant revises plans based on reviewer comments
  • Resubmitted for another round of review

6. Final Approval and Permit Issuance

Timeframe: 1–5 business days (once plans are cleared)

  • Permit issued and ready for pickup or download
  • Construction can begin once permit is posted onsite

How to Speed Up the Building Permit Process

While you can’t control the city’s workload, there are several steps you can take to accelerate approval:

✅ Work With a Commercial Architect

Firms like Maxx Designers understand local codes, jurisdiction-specific workflows, and how to prepare a clean, comprehensive submittal that reduces back-and-forth with plan reviewers.

✅ Use a Permit Expediter

These professionals specialize in navigating the bureaucracy of city departments and can flag potential issues before submission.

✅ Attend Pre-Application Meetings

Many cities offer pre-application or pre-submittal meetings. These sessions allow you to clarify code interpretations, zoning questions, and documentation requirements upfront.

✅ Submit Digitally (If Available)

Some cities offer online portals for uploading plans, tracking reviews, and paying fees. Digital submittals are often faster and easier to track.

✅ Avoid Common Mistakes

  • Missing consultant stamps
  • Incomplete plan sheets
  • Incorrect zoning data
  • Outdated code references

FAQs About Building Permits

Q: Do all projects require a building permit?

Not necessarily. Minor cosmetic upgrades (e.g., painting, flooring, cabinetry) may not require a permit. Always check with your local building department.

Q: Can construction start before the permit is issued?

No. Starting construction without a permit can result in legal penalties and project delays.

Q: Who is responsible for getting the permit—the owner, architect, or contractor?

It depends. In most cases, the architect prepares the drawings, and the owner or contractor applies for the permit. Some jurisdictions require specific licenses to pull commercial permits.

Q: Can permit approval be expedited?

Some cities offer expedited plan review services for an additional fee. However, availability is limited and eligibility varies.


Final Thoughts: Plan Ahead for Permitting Success

Getting a building permit is a critical milestone in your construction project, and understanding the timeline is key to setting realistic expectations. While simple projects may be approved in a few weeks, more complex developments can take several months.

With the right team—especially an experienced commercial architect who understands local regulations—you can minimize delays, reduce revision cycles, and keep your project on track.